This is Hostel at Panchgani www.mpforest.com.
Please submit your comments on the draft training guidelines of the front line staff.

   Capacity Development for Forest Management & Training of Personnel

  Item-wise Project Cost can be seen in the Table below

  Breakdown of Cost Original(Option1)
     
Foreign Currency Portion Local Currency Portion Total
                 
Total JICA Portion Others Total JICA Portion Others Total JICA Portion Others
                 
  Item (Mil. Yen) (Mil. Yen) (Mil. Yen) (Mil. Yen) (Mil. Yen) (Mil. Yen) (Mil. Yen) (Mil. Yen) (Mil. Yen)
                     
  Activities for Strengthening of Training System 0 0 0 65 65 0 65 65 0
                     
  Rehabilitation of Training Institute/ Schools 0 0 0 4,156 4,156 0 4,156 4,156 0
                     
  Trainings 0 0 0 47 47 0 47 47 0
                     
  Supporting Activities 71 0 71 272 271 1 343 271 72
                     
  Price Escalation 0 0 0 452 452 0 452 452 0
                     
  Physical Contingency 0 0 0 250 250 0 250 250 0
                     
  Land Acquisition 0 0 0 0 0 0 0 0 0
                     
  Administration Cost 0 0 0 262 0 262 262 0 262
                     
  Tax & Duties 0 0 0 210 0 210 210 0 210
                     
  Interest during construction 114 0 114 0 0 0 114 0 114
                     
  Commitment Charge 11 0 11 0 0 0 114 0 114
                     
  Total 196 0 196 5,714 5,241 473 5,910 5,241 669