   Capacity Development for Forest Management & Training of Personnel

 Project Cost can be seen in the Table below
         
Components   In INR (Crores)   In YEN (Millions)
         
PMU Cost   1.50   3.81
         
PMU / Steering Committee Cost   0.20   0.51
         
Preparation of Model Teaching Notes   0.10   0.25
         
Improvment of Infrastructure at CASFOS   0.30   0.76
         
Study Tour   0.40   1.02
         
Rehabilitation of SFTI's   155.40   394.72
         
Equipments for Training   7.90   20.07
         
                                              TOT   0.10   4.57
         
Reapartation of material for frontline staff   1.80   0.25
         
Monitoring & Evaluation   0.50   1.27
         
Consultancy Services   10.70   27.18
         
Price Escalation   17.80   45.21
         
Physical Contingencies   9.80   24.91
         
Loan   206.50   524.53
         
Host Govt. Cost        
         
Administrative Cost   10.70   27.18
         
VAT   8.30   21.08
         
                                  Total Project Cost   225.50   572.79